Battery storage facility

Hawthorn Grid Site - Battery Storage

Hawthorn Grid Site - Battery Storage is a battery storage facility in United Kingdom with a capacity of 49 MW, commissioned in 2024. It is operating and is owned by Harmony Energy Limited.

Its output is contracted under the Contract for Difference — Allocation Round 6, at a strike of £50.07/MWh (2012 prices) on a 15-year term.

Capacity
49 MW
Country
United Kingdom
Status
operating
Commissioned
2024
Owner
Harmony Energy Limited
Technology
Stand-alone
Support scheme
Allocation Round 6
Strike price
£50.07/MWh (2012 prices)

Sources: asset record from the Renewable Energy Planning Database; support scheme from the Renewable Energy Planning Database, strike price from the DESNZ allocation-round results (Open Government Licence v3.0) (Open Government Licence v3.0), in which the named party is the operator or applicant rather than a registered owner. All United Kingdom assets