Solar farm

Solarpark Wackersdorf solar project

Solarpark Wackersdorf solar project is a solar farm in Germany with a capacity of 3.4 MW, commissioned in 2024. It is operating and is owned by Solarpark Wackersdorf GmbH & Co. KG.

In 2024 it settled 267 MWh of electricity, a load factor of 0.9%. It sold essentially all of that volume outside EEG support — it is already merchant.

Peer comparison unavailable

Commissioned 2024, settled 2024 — a partial year of output over a full year of nameplate. Not comparable.

Capacity
3.4 MW
Country
Germany
Status
operating
Commissioned
2024
Owner
Solarpark Wackersdorf GmbH & Co. KG
Technology
PV
Measured output 2024
267 MWh
Load factor
0.9%
Grid connection
MS
State
Bayern

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE916089162587); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets