Solar farm

Greenotaurus Lehrte MS solar project

Greenotaurus Lehrte MS solar project is a solar farm in Germany with a capacity of 1.2 MW, commissioned in 2024. It is operating and is owned by Greenotaurus GmbH.

Its EEG support runs to the end of 2044, after which that output is sold at market prices.

Capacity
1.2 MW
Country
Germany
Status
operating
Commissioned
2024
Owner
Greenotaurus GmbH
Technology
PV
EEG support ends
2044
Grid connection
MS
State
Niedersachsen

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); ownership established by research against marktstammdatenregister.de (SEE951814151504); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets