Solar farm

KPAR015 (Hamm II) solar project

KPAR015 (Hamm II) solar project is a solar farm in Germany with a capacity of 3.5 MW, commissioned in 2024. It is operating and is owned by Sunrock Solarproject 1 GmbH & Co. KG.

In 2024 it settled 515 MWh of electricity, a load factor of 1.7%. That volume was settled under EEG support.

Its EEG support runs to the end of 2042, after which that output is sold at market prices.

Peer comparison unavailable

Commissioned 2024, settled 2024 — a partial year of output over a full year of nameplate. Not comparable.

Capacity
3.5 MW
Country
Germany
Status
operating
Commissioned
2024
Owner
Sunrock Solarproject 1 GmbH & Co. KG
Technology
PV
Measured output 2024
515 MWh
Load factor
1.7%
EEG support ends
2042
Grid connection
MS
State
Nordrhein-Westfalen

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE926156473119); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets