Wind farm

Güstow wind farm

Güstow wind farm is a wind farm in Germany with a capacity of 40 MW, commissioned in 2023. It is operating and is owned by GREE Güstow GmbH & Co. KG.

In 2024 it settled 65.3 GWh of electricity, a load factor of 18.6%. That volume was settled under EEG support. This figure is apportioned across units of the same site that share a registry entry.

Its EEG support runs to the end of 2034, with later phases to 2043, after which that output is sold at market prices.

Measured performance vs peers
18.6%
This assetCohort median 23.8%Middle half

This asset produced at 18.6% of nameplate in 2024 — the 21st percentile of German wind commissioned 2020 or later (140 assets with metered output). Its volume is apportioned across phases sharing one registry entry, so treat the figure as an estimate for this unit and exact for the site.

Capacity
40 MW
Country
Germany
Status
operating
Commissioned
2023
Owner
GREE Güstow GmbH & Co. KG
Technology
Onshore
Measured output 2024
65.3 GWh
Load factor
18.6%
EEG support ends
2034
Peer percentile
21st
Grid connection
HS
State
Brandenburg

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE952437191137); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets