Wind farm

Gadegast wind farm

Gadegast wind farm is a wind farm in Germany with a capacity of 22 MW, commissioned in 2016. It is operating and is owned by Windpark Gadegast GmbH & Co. KG.

In 2024 it settled 54.1 GWh of electricity, a load factor of 28.1%. That volume was settled under EEG support.

Its EEG support runs to the end of 2036, after which that output is sold at market prices.

Measured performance vs peers
28.1%
This assetCohort median 24.7%Middle half

This asset produced at 28.1% of nameplate in 2024 — the 75th percentile of German wind commissioned 2015-2019 (215 assets with metered output).

Capacity
22 MW
Country
Germany
Status
operating
Commissioned
2016
Owner
Windpark Gadegast GmbH & Co. KG
Technology
Onshore
Measured output 2024
54.1 GWh
Load factor
28.1%
EEG support ends
2036
Peer percentile
75th
Grid connection
MS
State
Sachsen-Anhalt

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE990357990812); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets

←CapexAtlas|ScreenerMap