Norstedt-Wind is a wind farm in Germany with a capacity of 19 MW, commissioned in 2014. It is operating and is owned by Norstedt-Wind.

In 2024 it settled 44.9 GWh of electricity, a load factor of 27.0%. That volume was settled under EEG support.

Its EEG support runs to the end of 2034, after which that output is sold at market prices.

Measured performance vs peers
27.0%
This assetCohort median 21.9%Middle half

This asset produced at 27.0% of nameplate in 2024 — the 83rd percentile of German wind commissioned 2010-2014 (128 assets with metered output).

Capacity
19 MW
Country
Germany
Status
operating
Commissioned
2014
Owner
Norstedt-Wind
Technology
Onshore
Measured output 2024
44.9 GWh
Load factor
27.0%
EEG support ends
2034
Peer percentile
83rd
Grid connection
HS/MS
State
Schleswig-Holstein

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE910700730872); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets