Wind farm

Hohegaste wind farm

Hohegaste wind farm is a wind farm in Germany with a capacity of 12 MW, commissioned in 2017. It is operating and is owned by Windenergiepark Hohegaste GmbH & Co KG.

In 2024 it settled 29.2 GWh of electricity, a load factor of 27.8%. That volume was settled under EEG support.

Its EEG support runs to the end of 2037, after which that output is sold at market prices.

Measured performance vs peers
27.8%
This assetCohort median 24.7%Middle half

This asset produced at 27.8% of nameplate in 2024 — the 72nd percentile of German wind commissioned 2015-2019 (215 assets with metered output).

Capacity
12 MW
Country
Germany
Status
operating
Commissioned
2017
Owner
Windenergiepark Hohegaste GmbH & Co KG
Technology
Onshore
Measured output 2024
29.2 GWh
Load factor
27.8%
EEG support ends
2037
Peer percentile
72nd
Grid connection
HS/MS
State
Niedersachsen

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE929567258306); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets