Solar farm

Solarpark Rassnitz solar farm

Solarpark Rassnitz solar farm is a solar farm in Germany with a capacity of 7.1 MW, commissioned in 2011. It is operating and is owned by Solarpark Rassnitz GmbH.

In 2024 it settled 7.5 GWh of electricity, a load factor of 12.1%. That volume was settled under EEG support.

Its EEG support runs to the end of 2031, after which that output is sold at market prices.

Measured performance vs peers
12.1%
This assetCohort median 10.5%Middle half

This asset produced at 12.1% of nameplate in 2024 — the 95th percentile of German solar commissioned 2010-2014 (2,063 assets with metered output).

Capacity
7.1 MW
Country
Germany
Status
operating
Commissioned
2011
Owner
Solarpark Rassnitz GmbH
Technology
PV
Measured output 2024
7.5 GWh
Load factor
12.1%
EEG support ends
2031
Peer percentile
95th
Grid connection
MS
State
Sachsen-Anhalt

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE939126201988); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets